Project Data

Softdrill NL   

 

When editing project data, the following dialog box will appear:

 

Project data

 

Print header data

Data input here will appear in the header of the printed lookahead schedule.

 

Schedule calculation (initial values)

This data is used as the initial value in the Operations and Personnel on Board (POB) calculations.

 

 

Working time

Full day working

No restriction, working from 00:00 to 24:00 hrs. If non-working days are not applied (see 3 below) then the Working Schedule is defined as Unrestricted.

 

Restricted working hours

Specify working hours. Work From must be earlier than Work To. If Working From and To are defined (in combination with non-working days (see 3 below) or not, the Working Schedule is defined as Restricted.  Setting working hours may be limited by the duration of no split operations.

 

Non-working days

Input of non-working days (e.g. festive days, etc.).  As many dates as required may be input.  When active  (checked), the Working Schedule is defined as Restricted, regardless of the working hours selected ('All day' or 'Part of the day'). Defining active non-working days may be limited by the duration of no split operations.

 

 

Logo

Select logo

Click to open a logo from file.

 

Save logo

Save current logo to file.

 

Logo

Right-click either logo to open a quick menu (e.g. to copy & paste logo's).

 

 

 